PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.

In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent

"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).

Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power. 

MRT Project Has Touched 93.45 Percent

"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.

Linked News
Popular News indeks
  1. Pademangan Health Center Promotes 3M Plus to Prevent Dengue Fever

    access_time14-04-2026 remove_red_eye825 personAnita Karyati
  2. Jakarta Provincial Government Fully Supports BTN JAKIM 2026

    access_time14-04-2026 remove_red_eye739 personDessy Suciati
  3. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye715 personFakhrizal Fakhri
  4. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye679 personDessy Suciati
  5. Job Absorption Rises in Jakarta

    access_time17-04-2026 remove_red_eye583 personDessy Suciati