Pemasangan Track Kereta MRT Jakarta Capai Lebih Dari 80 Persen

MRT Railway Line Installation Has Touched 80 Percent

PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.

In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent

"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).

Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power. 

MRT Project Has Touched 93.45 Percent

"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1709 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1481 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1335 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1120 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye815 personDessy Suciati