Pemasangan Track Kereta MRT Jakarta Capai Lebih Dari 80 Persen

MRT Railway Line Installation Has Touched 80 Percent

PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.

In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent

"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).

Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power. 

MRT Project Has Touched 93.45 Percent

"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2355 personDessy Suciati
  2. Immersive Room and Glowing Forest Attractions Enliven Eid at TMII

    access_time26-03-2026 remove_red_eye998 personFakhrizal Fakhri
  3. Deputy Governor Watches Pelangi di Mars with Orphans

    access_time27-03-2026 remove_red_eye826 personTiyo Surya Sakti
  4. 292 East Jakarta Personnel Mobilized for Eid Return Rush

    access_time25-03-2026 remove_red_eye774 personNurito
  5. Jakarta's Mudik to Jakarta Program Hits Rp21 Trillion in Transactions

    access_time25-03-2026 remove_red_eye757 personFakhrizal Fakhri