Pemasangan Track Kereta MRT Jakarta Capai Lebih Dari 80 Persen

MRT Railway Line Installation Has Touched 80 Percent

PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.

In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent

"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).

Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power. 

MRT Project Has Touched 93.45 Percent

"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.

Linked News
Popular News indeks
  1. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1024 personFakhrizal Fakhri
  2. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye978 personDessy Suciati
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye632 personAldi Geri Lumban Tobing
  4. Pramono: Jakarta Ready to Pay Out Holiday Bonus to ASN

    access_time04-03-2026 remove_red_eye563 personDessy Suciati
  5. Grab Your Umbrellas: Heavy Rain Expected to Soak Jakarta Today

    access_time06-03-2026 remove_red_eye562 personDessy Suciati